Ohio River Bridges - East End Crossing - ORB EEC Project Schedule

Global assisted Parsons Transportation Group in reviewing and monitoring Ohio River Bridges - East End Crossing project schedule which was being developed by the builder of the project. Global reviewed baseline schedules and monthly schedule updates submitted by the developer of the project. Feedback was provided to the Parsons Project Controls Manager and Project Manager on the findings of the review. Construction budget for the project was $780 million dollars. Project schedule consisted of over 5000 activites and over 11000 relationships. 

Global also assisted with Earned Value Analysis of the project.